Timely planning — from project drawings to installation without rushing.
Windows and doors are among the items with the longest lead times on a building site. They are made to individual dimensions, so you cannot order them tomorrow and install them the day after. Without timely planning, closing the building envelope is delayed, along with interior work. This article explains how to fit window and door deliveries into the construction schedule.
Installing windows and doors is a key construction stage: once the building is enclosed, interior work can safely begin. If windows are delayed, so are the tasks that depend on them: plastering, floors, finishes and heating. Window delivery should therefore be treated as a critical-path item, not a purchase to leave until later.
Lead times normally start from order confirmation, not from the first conversation.
The simplest approach is to work backwards from the date the windows need to be installed:
Practical advice: start discussing windows at least **3 months before the planned installation**. This gives you time to agree the specification, arrange measurements and receive the finished windows without rushing.
During construction, actual opening dimensions can differ slightly from the drawings, so a two-step approach is useful:
This makes the schedule clear early in the project while ensuring the order uses real dimensions.
Finalise the specification before ordering
A clear specification covering dimensions, profiles, glazing, colour and opening type helps avoid changes after production begins.
Arrange measurements in good time
Schedule measurements once the openings are formed, but before the ordering deadline.
Split deliveries where needed
On larger projects, deliveries can be split to match construction stages.
Coordinate the schedule with one contact person
The fewer parties involved, the easier it is to coordinate dates.
Allow a contingency
Particularly in the cold season or on complex projects, leave a small time buffer.
We offer one point of contact for the whole project, from the initial consultation and on-site measurement to delivery, installation and aftercare. Our own team carries out installation, followed by a 30-day comfort check and an inspection after 180 days. If the schedule changes, we communicate clearly and in good time.
Send us your project plans or get in touch for an initial assessment of solutions and lead times. Consultation and on-site measurement are free.
Send plans
Window and door project specifications
Preparing for window installation
Precise measurements
A private house under construction with installed windows